Post Production Schedule

“RHINOCEROS EYES” recut

as of Wednesday, February 15, 2007 1:31 PM

Post Production Supervisor (213/821-2792)

This schedule is a working, changing document, which we will change on a weekly basis.

Week 1

January 19

Begin editing.
Digitize first scene/s.

Week 2

January 26

Screen first scenes. 
Continue editing next two scenes.
Add music to first scene.
Re-evaluate post schedule.

Week 3

February 2

Begin editing more scenes. 
Recut earlier scenes.
Continue with adding music to scenes.
Re-evaluate post schedule.

Week 4

February 9

Continue editing. 
Continue recutting.
Add sound effects as necessary.
Re-evaluate post schedule.

Week 5

February 16

Continue editing.
Add more scenes.
Re-evaluate post schedule.

Week 6

February 23

Continue editing.
Recut all scenes for full screening.
Add music.
Re-evaluate post schedule.

Week 7

March 1

All scenes must be ready by 12noon.

March 2

Screen entire film (v199). 
Recut plan.
Re-evaluate post schedule.

Week 8

March 9

Screen parts of second cut.
Continue re-editing.
Reevaluate post schedule.
Any additional music needed?

Week 9

March 14-19

SPRING RECESS. Post will be open (??)

Week 10

March 22

Scenes finished by 12noon for build.

March 23

Screen complete second cut (v299).
Discuss musical choices.
How is style working?
Reevaluate post schedule.

Week 11

March 30

Recut for next week.
Reevaluate post schedule.

Week 12

April 5

Scenes finished by 12noon for build.

April 6

Screen third complete cut (v399).
Reevaluate post schedule.

Week 13

April 12

Scenes finished by 12noon for build.

April 13

LOCK CUT (v499).
Spotting sessions.
Begin sound and music work.
Create EDLs and Cut lists
.
Reevaluate post schedule.

Week 14

April 20

Lock sound and music.
Make Quicktime movies of finished cut for DVD.
Reevaluate post schedule.

Week 15

April 27

Create assets and menus for DVD.
Create artwork (Photoshop).
Resume work to finish up.
Reevaluate post schedule.

Week 16

May 4

Finish DVD building. Party!!